Key Facts

Type: Class IV bikeways
Location: On 4th Street from Grand Avenue to Tamalpais Avenue, and on Tamalpais Avenue from 4th Street to Mission Avenue
Managing Agency: City of San Rafael
Cost: $5.4M
Funding: $4.3M for design and construction (ATP Cycle 7, 2025)
Status: In Design
Project Update: Project won full funding in 2025. Design effort has not yet kicked off as of June 2025.
Protected bikeway with green painted pavement and white bike and arrow paint in San Rafael

Benefits of the Project

This project will connect several existing bikeway and pathway projects in the middle of Downtown San Rafael. These are the Lincoln Hill pathway north of Mission Avenue, the SMART pathway south of 2nd Street, and the Grand Avenue bikeway ending on 4th Street. This project brings riders from all directions to Downtown San Rafael where they can access goods and services, as well as the SMART train or bus service at the San Rafael Transit Center.

What You Can Do

No action needed at present. When public meetings take place, there will be a need to support the planned parking removal on 4th St. and Tamalpais Ave.

Project Photos/Renderings

Stay Informed About This Project

Complete this form to join the Road Advocacy Interest List